Are we making money against what we quoted? Jobs on the floor burn labour today, so budget consumed and margin are live signals here. Booked-but-not-started work is reported separately so it can't flatter the numbers.

In production · Fabrication + Integration

Estimated GP

36%

$633.6K projected on $1.8M quoted

Realized GP

36%

$267.2K on $737.5K invoiced

Budget consumed

87%

$1.1M of $1.3M budgeted cost

Jobs over budget

2

of 9 in production

Production portfolio — quoted vs actual

Buffer is held back, not spent

CategoryQuoted sellActualVariance
Labour$491,756$404,398$87,358
Materials$741,488$660,575$80,913
Other—$59,120-$59,120
Buffer$62,037——
Total$1,757,704$1,124,093$633,611
Invoiced to date—$737,549—

Cost budget consumed: $1,124,093 of $1,295,281

Remaining to invoice

$1M

production jobs

Booked revenue

$2.3M

8 jobs · 4 Awarded · 4 Released

$65,251 of early engineering cost is already posted against these — excluded from the production figures.

Labour quote accuracy — in production

Across 9 jobs with logged hours, labour is running at $73.30/hr against $86.84/hr quoted, and 5,517 hours burned against 5,663 estimated — -3% on hours.

A rate that holds while hours slip means the estimate is short, not the shop — that is a fix in the quoting template, not on the floor.

Fabrication

On the floor — chassis, powder coat, assembly

JobCustomerUnitsQuotedActualConsumedShip target
J-2614 Emergency Ops CenterTrailhead Community District27$90,551$79,877
110%
over
J-2603 Elementary Wing RetrofitNorthgate Health Partners137$375,441$246,669
95%
2026-12-25
J-2608 ED Workstation ProgramLakeshore County Schools42$98,093$70,777
95%
2026-10-15
J-2604 District Device RolloutNorthgate Health Partners118$354,204$200,293
81%
2026-10-29
J-2613 Mobile Testing ProgramSandy Shores Unified72$216,461$129,065
81%
2026-09-28
J-2609 Nursing Floor CartsRidgeway Memorial87$189,074$98,845
65%
2026-11-07

Integration

Power, cable management, imaging and QA

JobCustomerUnitsQuotedActualConsumedShip target
J-2602 Emergency Ops CenterBeacon Insurance15$34,093$32,750
116%
over
J-2607 Telehealth Cart FleetNorthline Logistics65$123,344$84,078
100%
2026-10-02
J-2612 ED Workstation ProgramOakhaven Unified160$276,443$181,739
84%
2026-10-01

Awarded

Awarded — booked, not started

JobCustomerUnitsQuotedActualConsumedShip target
J-2605 ED Workstation ProgramTrellis Foods107$184,039$6,707
5%
2026-12-11
J-2610 Bond Program Phase 2Harbor Point Hospital96$276,703$6,586
3%
2026-09-11
J-2600 STEM Lab BuildoutCopper Hills Unified152$274,307$6,162
3%
2026-09-13
J-2615 1:1 Chromebook RefreshEmerald City Schools83$215,890$2,897
2%
2026-09-24

Released

Released for build — booked, not started

JobCustomerUnitsQuotedActualConsumedShip target
J-2616 Elementary Wing RetrofitUnity Health Alliance154$442,613$20,913
6%
2026-12-23
J-2601 Nursing Floor CartsSandy Shores Unified171$334,870$10,543
4%
2026-12-10
J-2606 Campus Locker BankBirchwood Public Schools185$439,933$9,913
3%
2026-11-28
J-2611 Summer Refresh PackageRedstone County Schools61$146,143$1,530
1%
2026-11-30